Intensive Upgrade Of Wellington Train System Starts

 

Work has begun on KiwiRail’s intensive period of construction on the Wellington rail network.

Most of the activity will be focused at the entrance to Wellington Station where a third main line is being installed.

Once it is operational mid next year,  the third line will increase capacity and remove a bottleneck at a busy point in the network.

Track entrance to Wellington railway station

Work over the next 10 days at Wellington Station includes:

  • Removing existing track Removing then restoring the overhead wires which power electric trains
  • Building the track formation (foundations)
  • Laying new track
  • Begin resurfacing some platforms

Elsewhere on the network, improvements will continue on:

  • the reconstruction of Pukerua Bay platform
  • re-alignment of tracks at Western Hutt, Melling and Kaiwharawhara stations
  • the upgrade of the overhead line system which powers Wellington’s electric trains

Tags:

 
 
 

0 Comments

 

You can be the first one to leave a comment.

 

Leave a Comment

 




XHTML: You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>